The Houston County Board of Education is lining up a $60 million renovation and expansion of Perry High School at 1307 North Avenue in Perry, GA. The district's Request for Proposals 27-504, titled "Additions and Renovations to Perry High School," seeks a Construction Manager at Risk to deliver the work in four phases, with preconstruction for Phase 1 scheduled to begin in December 2026 and the final phase scheduled to wrap up in August 2031.
A separate bid, Invitation to Bid 27-503, covers new baseball and softball fields on the Perry High campus, with bids due November 3, 2026. Together, the two solicitations represent a multi-year investment in one of Perry's main school campuses, and they matter to families, homeowners, and buyers across Perry and the rest of Houston County.
The project schedule runs nearly five years, and the campus is expected to stay open while crews work. Here is what the district has published so far, what is still unknown, and what it means for real estate decisions in the Perry High School attendance area.
Key Takeaways
• Houston County Schools RFP 27-504 describes "Additions and Renovations to Perry High School" at 1307 North Avenue, Perry, GA 31069, with a total budget of $60,000,000 across multiple phases.
• The RFP lists four phase budgets: Phase 1 at $22 million, Phase 2 at $2 million, Phase 3 at $28 million, and Phase 4 at $8 million.
• Phase 1 construction is scheduled from November 2027 to April 2029, and Phase 4 is scheduled from April to August 2031, according to the RFP.
• The RFP states the Perry High campus will remain active during construction, and the architect is Altman + Barrett Architects.
• ITB 27-503 covers new baseball and softball fields, structures, walks and parking at Perry High, with bids due November 3, 2026 and SRJ Architects as architect.
• A district project update says Phase 1 is scheduled for the current E-SPLOST and Phase 2 for the next E-SPLOST cycle, which does not match the four phases in the RFP.
How much will the Perry High School renovation cost?
The district's RFP sets the total project budget at $60,000,000, described as "inclusive of multiple phases." The scope covers site development, new construction, and renovation and/or modifications to the existing Perry High School campus. The district is using a Construction Manager at Risk delivery method, which means one construction firm joins the team during design and then commits to a Guaranteed Maximum Price (GMP) for each phase before building it.
That GMP-per-phase structure is worth understanding. It means the $60 million figure is a budget, not a signed contract price. Each phase gets its own price commitment closer to the time it is built, so the final scope of later phases could shift as design and pricing develop.
Perry High School RFP 27-504: phase budgets and construction windows
Phase | Budget | Construction window |
Phase 1 | $22,000,000 | November 2027 to April 2029 |
Phase 2 | $2,000,000 | May 2029 to August 2029 |
Phase 3 | $28,000,000 | August 2029 to December 2030 |
Phase 4 | $8,000,000 | April 2031 to August 2031 |
Total | $60,000,000 | Preconstruction for Phase 1 begins December 2026 |
The table shows the money is concentrated in Phases 1 and 3, which together account for $50 million of the $60 million budget and run from late 2027 through the end of 2030. For Perry homeowners and buyers, that means the most visible construction activity on North Avenue is likely to fall in those two windows. The shorter Phase 2 is scheduled for summer 2029, when school is out, and Phase 4 again lands in a spring to summer window. The district has not published square footage, building layouts, or a list of which buildings change in which phase; the RFP's site attachment is an image without readable details. Anyone planning around the project should treat the dates as a schedule in a procurement document, not a guarantee.
When will construction start at Perry High School?
According to the RFP timeline, proposals were due October 27, 2026, the shortlist was set for October 30, interviews were scheduled for November 3, and the district planned to announce the selected contractor on November 11, 2026. As of November 4, 2026, no contractor announcement has been posted.
After selection, preconstruction services for Phase 1 run from December 2026 to October 2027. Physical Phase 1 construction is scheduled to begin in November 2027. That means families with students at Perry High in the 2026 to 2027 school year are unlikely to see major building work on the main campus, while students enrolled from fall 2027 onward will likely attend during some stage of construction.
• October 27, 2026: proposals due
• October 30, 2026: shortlist
• November 3, 2026: interviews
• November 11, 2026: planned contractor announcement
• December 2026 to October 2027: Phase 1 preconstruction
• November 2027: Phase 1 construction scheduled to begin
What is being built for Perry High School baseball and softball?
Invitation to Bid 27-503, "Baseball-Softball Improvements Phase 3 Perry HS," is a separate project from the $60 million renovation. The bid covers new baseball and softball fields, structures, walks and parking. It also includes demolition of existing asphalt, concrete and utilities.
The bid documents place the site at the parking lot south of the existing softball field, off Park Avenue and Parkway Drive. The architect is SRJ Architects, and bids were due November 3, 2026. The district has not published a dollar figure for this athletic project in the bid notice reviewed for this article.
For nearby residents on and around Park Avenue and Parkway Drive, this is the piece of work that changes the streetscape most directly, since it converts an existing parking area into athletic facilities with new parking.
How is the Perry High School project being funded?
E-SPLOST is the education special purpose local option sales tax that pays for many school capital projects in Houston County. The district's E-SPLOST 2022 to 2027 page lists a Perry High School "Classroom addition and site improvement." A district project update document states that "Perry High Renovation and Classroom Addition: Phase 1 is scheduled for the current E-SPLOST" and that "Phase 2 will be in the next E-SPLOST cycle."
Those statements describe two phases tied to two E-SPLOST cycles, while RFP 27-504 lays out four phases with a combined $60 million budget. The district has not published a document that ties the full $60 million to one tax or one cycle, so this article does not either. The safest reading is that Phase 1 is planned within the current E-SPLOST and later work depends on future funding, but the district has not published that breakdown in a single place.
Because the district ties Phase 2 to a future E-SPLOST cycle, the later phases are the part of the schedule most worth watching.
Does the Perry High School renovation affect home values in Perry, GA?
No published study measures how this specific project will affect home values, and any claim of a fixed percentage bump would be invented. What can be said is that school facilities are one of the factors buyers weigh when choosing between Perry, Warner Robins, Bonaire, Kathleen and Centerville, and a published, funded plan for a campus is information buyers ask about.
Construction also has short-term effects that matter for anyone listing near the campus: contractor traffic, staging areas, and changes to parking and athletic facilities. The RFP says the campus stays active throughout, which points to phased work rather than a full closure. Sellers and buyers near North Avenue, Park Avenue and Parkway Drive should factor both the long-term improvement and the multi-year construction window into timing decisions.
Should I sell my Perry, GA home before or after the Perry High School construction?
Perry High School construction is scheduled to begin in November 2027 and run in phases through August 2031, so homes near the campus have a defined window before the heaviest work begins.
My take: if you live close to North Avenue or the Park Avenue and Parkway Drive side of campus and you already plan to move in the next year or so, the 2027 spring market lands before Phase 1 construction is scheduled to start. If you are staying long term, I would not rush. I use this project as a selling point when it is accurate: a district with a published, phased plan for its high school is a story I can tell buyers. I will pull recent sales near the campus and show you how they compare to the rest of Perry before you decide.
Long-tail keyword targets (remove before publishing): sell home near Perry High School | Perry GA home value school construction | when to sell house Perry GA | Perry GA seller market 2027
Is it a good time to buy a home in the Perry High School zone?
Houston County Schools has published a $60 million, four-phase plan for Perry High School with work scheduled from late 2027 into 2031, so buyers in the Perry High area are buying into a campus with a defined improvement schedule.
When I work with buyers looking in Perry, I tell them to verify the school zone for every address with Houston County Schools, because attendance lines do not always follow city limits. I also tell them to think about where they will be in 2029 and 2030, when the largest phase is scheduled. If you have a student who will be at Perry High during construction, that matters. If you are buying for the long run, a renovated campus is part of what you are buying. I can help you compare homes in the Perry High zone against Warner Robins and Bonaire options so the decision is about the whole picture.
Frequently Asked Questions
How much is the Perry High School renovation in Perry, GA?
Houston County Schools RFP 27-504 sets a total budget of $60,000,000 for additions and renovations to Perry High School. The budget is inclusive of multiple phases. The four phases are budgeted at $22 million, $2 million, $28 million and $8 million. Each phase will receive its own Guaranteed Maximum Price from the construction manager.
Where is Perry High School located?
Perry High School is at 1307 North Avenue, Perry, GA 31069, according to the district's RFP. The school is part of the Houston County School District. The campus serves students in Perry and parts of surrounding Houston County. Families should confirm attendance zones for any address directly with the district.
When does construction start at Perry High School?
Phase 1 construction is scheduled from November 2027 to April 2029, according to RFP 27-504. Preconstruction for Phase 1 is scheduled from December 2026 to October 2027. The schedule is part of a procurement document and could change. The district planned to announce the selected contractor on November 11, 2026.
When will the Perry High School project be finished?
The RFP schedules Phase 4 construction from April 2031 to August 2031, which is the last listed phase. Phase 3, the largest at $28 million, is scheduled from August 2029 to December 2030. Final completion depends on funding and contractor pricing for each phase. The district has not published a guaranteed completion date.
Will Perry High School stay open during construction?
Yes. The RFP states the campus remains active during construction. That is one reason the work is divided into phases. Students, staff and visitors should expect construction zones and changes to parking or access at different points between 2027 and 2031.
Who is the architect for the Perry High School renovation?
RFP 27-504 lists Altman + Barrett Architects as the architect for the additions and renovations. The separate baseball and softball project under ITB 27-503 lists SRJ Architects. A Construction Manager at Risk will be selected for the renovation through the RFP process.
What is the Perry High School baseball and softball project?
Invitation to Bid 27-503 covers new baseball and softball fields, structures, walks and parking at Perry High School. The work includes demolition of existing asphalt, concrete and utilities. The site is the parking lot south of the existing softball field off Park Avenue and Parkway Drive. Bids were due November 3, 2026.
Is the Perry High School project paid for by E-SPLOST?
The Houston County Schools E-SPLOST 2022 to 2027 page lists a Perry High School classroom addition and site improvement. A district update states Phase 1 is scheduled for the current E-SPLOST and Phase 2 for the next E-SPLOST cycle. That two-phase description differs from the four phases in the RFP. The district has not published one document tying the full $60 million to a single funding source.
How big is the Perry High School addition?
The square footage and building list have not been published in readable form. The RFP's site attachment is an image without readable details. The RFP describes the work as site development, new construction, and renovation and/or modifications. More detail is likely once a construction manager is selected and design advances.
What is a Construction Manager at Risk?
A Construction Manager at Risk is a contractor hired early to advise during design and then build the project under a Guaranteed Maximum Price. Houston County Schools is using this method for Perry High School with a GMP for each phase. The approach lets the district price phases one at a time. For this project the district is selecting the construction manager through proposals, a shortlist and interviews.
Does the Perry High School project affect homes for sale in Perry, GA?
No published data measures the effect of this project on Perry home values. School facilities are one factor buyers weigh when comparing Perry, Warner Robins, Bonaire, Kathleen and Centerville. Homes near North Avenue, Park Avenue and Parkway Drive may see construction traffic during scheduled phases from 2027 to 2031. Buyers should confirm school zones with Houston County Schools for each address.
About the Author
William Walton-Dean is a licensed REALTOR® with Walton Dean Realty, operating under Real Broker LLC, serving buyers and sellers across Houston County, Georgia, including Perry, Warner Robins, Bonaire, Kathleen, Byron, and the surrounding Middle Georgia housing market. He brings a data-driven, hyper-local approach to both residential and commercial transactions, working with first-time buyers, move-up sellers, investors, and families relocating to the area, including those tied to Robins Air Force Base. Drawing on a prior career as a C-level executive, he helps buyers and sellers at every price point make clear, confident decisions backed by real market insight.
📱 478-371-7069
Walton Dean Realty | Real Broker LLC
Buying or Selling in Perry, GA? Let's Talk About What the Perry High Project Means for You
I track school and development projects across Houston County so my clients can time their moves with real information. Send me a message and I will walk you through homes and recent sales near Perry High School.
William Walton-Dean | Walton Dean Realty
📱 478-371-7069
A More Strategic Approach to Real Estate
Disclaimer: This article is for general information only and is based on Houston County Schools procurement documents that may change. Confirm school attendance zones, construction schedules and funding with Houston County Schools before making a buying or selling decision.